List of Required Tools and Consumables

Tool and Equipment Requirements

No.Item NameModel/Specification (Accuracy)UnitQty.Remarks
1Slotted screwdriver2、4、6、8"pcs1
2Phillips screwdriver2、4、6、8"pcs1
3Wrenchpcs1
4Multimeterpcs1
5Clamp meterpcs1
6Insulation testerpcs1
7Ethernet cableCAT5Epcs1
8USB‑485 cablepcs1
9Digital storage oscilloscope(Not required)pcs1
10Power quality analyzer(Not required)pcs1

Consumables List

No.Item NameModel/SpecificationUnitQtyRemarks
1Electrical tape……pcs1……
2Plastic cable tiespcs1

Inspection and Maintenance

Routine Inspection

Power-on Inspection

Perform routine inspection on the system, observe the status of equipment indicators and software monitoring information.

ItemInspection ContentIntervalRemarks
1. LED Screen
LED ScreenCheck whether the LED screen lights up normally during system operation.Once every 6 months
2、Battery
Battery IndicatorCheck whether all indicators on batteries and high-voltage box are lit normally.Once every 6 months
Abnormal NoiseCheck for any abnormal noise during system operation.Once every 6 months
3、Inverter
DisplayCheck that all voltage, power and current data on the display are normal.Once every 6 months
Energy Storage Inverter CommunicationCheck that communication is normal.Once every 6 months
Energy Storage Inverter Operating StatusCheck history for fault records.Once every 6 months
Energy Storage Inverter Fault LogRead error messages and warnings, and export fault records.Once every 6 months
Circuit BreakerCheck all circuit breakers via fault logs.Once every 6 months
FanCheck for fan faults via fault logs.Once every 6 months
Functional TestCheck functions such as start/stop of inverter and on/off of circuit breakers.Once every 2 years

Power-off Inspection

After the equipment has been in operation for a period of time, a power-off inspection shall be carried out.

ItemInspection ContentIntervalRemarks
Battery
AppearanceCheck for damage or rust on all batteries and high‑voltage box.Once every 6 months
Battery FixingCheck that all battery fixing bolts are tightened.Once every 6 months
Battery GroundingCheck that the battery is properly grounded. Ensure good electrical connection between the rear surface of the battery box front cover, the battery rack surface and the grounding point (continuity is verified with a multimeter).Once every 6 months
High‑voltage Box FixingCheck that the high‑voltage box is securely fixed; the front panel is tightly attached to the battery rack and all screws are locked.Once every 6 months
High‑voltage Box Molded Case Circuit BreakerCheck that the molded case circuit breaker of the high‑voltage box is in the normally closed position.Once every 6 months
Battery ConnectionCheck that the cables between batteries are securely locked;Check whether the connection terminals of the battery power cables are damaged, deformed or show signs of overheating;Check whether the battery terminals are provided with insulation protection.Once every 6 months
Connection Between Battery and High‑voltage BoxCheck whether the connection terminals of the high‑voltage box power cables are damaged or deformed.Once every 6 months
Cable FixingCheck that the connecting cables are securely fastened.Once every 6 months
Cable AgingCheck whether the cables are aged or damaged.Once every 6 months
2.Inverter
Energy Storage Inverter GroundingCheck that the grounding cable of the energy storage inverter is securely connected.Once every 6 months
Energy Storage Inverter FixingCheck that all bolts at the mounting points of the energy storage inverter are tightened.Once every 6 months
Energy Storage Inverter CablesCheck whether the terminals of the energy storage inverter cables are aged or damaged.Once every 6 months

Routine Maintenance

Power-on Maintenance

Maintenance ItemMaintenance ContentInterval
1.Battery
Battery Capacity CalibrationComplete charge and discharge cyclesOnce every 3 months
Battery Data AnalysisAnalyze BMS data (to be completed by AlphaESS engineers)Once every 6 months
Check the switching function of the high‑voltage box circuit breakerInspected locally with the assistance of AlphaESS engineersOnce every 6 months
heck whether the DC‑side insulation resistance is within a reasonable rangeIf no insulation fault is reported by the BMS during normal system operation, the insulation resistance is within the reasonable rangeOnce every 6 months

Power-off Maintenance

Maintenance ItemMaintenance ContentInterval
1.Battery System
Battery GroundingPerform grounding test with a multimeterOnce every 3 months
Battery FixingCheck whether the battery is firmly fixed on the battery rackOnce every 6 months
High-voltage Box GroundingPerform grounding test with a multimeterOnce every 3 months
Battery LabelCheck for damage; replace with the same label if damagedOnce every 3 months
2.Inverter
AppearanceCheck whether the inverter appearance is damaged or deformedOnce every 6 months
Inspection of live part screws, power cables and communication cables of energy storage inverterCheck that screws, power cables and communication cables are connected properly, without jamming or looseness, and connectors are not looseOnce every 6 months
Cleaning and anti-rust inspection of energy storage inverterClean the energy storage inverter and check whether cable connectors are rustedOnce every 6 months
Power circuit connectionCheck and tighten power cables if loose; check whether power and control cables are damaged; pay special attention to the contact surface between cable insulation and metal; check whether insulation ties are detached from cable terminalsOnce every 6 months
Clean ventilation baffle or air ductAfter power off, remove dust with a brush or vacuum cleanerOnce every 6 months
SafetyCheck warning labels and replace if necessaryOnce every 6 months

After all equipment has stopped operating, the following precautions shall be noted during maintenance:

· Observe relevant safety standards and regulations during operation and maintenance.

· Disconnect all electrical connections to ensure the equipment is de-energized.

· The number of maintenance personnel shall be no less than two during maintenance.

· The equipment shall be repaired by qualified professionals. Unauthorized disassembly of the equipment is strictly prohibited.

· Appropriate protective measures shall be taken during maintenance, such as insulating gloves, insulating shoes and earplugs.

· Energy storage systems are usually located away from urban areas. Relevant emergency rescue measures shall be established for implementation when necessary.

· When the entire system remains idle for a long time (i.e., the battery has not been charged for two weeks or longer), the battery SOC shall be charged to 30%~50% to prevent over-discharge.

· If any situation cannot be explained in this manual, please contact us in a timely manner.

Storage Environment

CategoryNameStorage Environment
Finished Product

Battery

High-voltage Box

1. Store batteries indoors in cartons, and control indoor humidity below 65%. Close doors and windows tightly when external humidity is high to prevent moisture ingress.

2. 2. Carton stacking and environment requirements:

3. ① Place cartons on wooden shelves at least 25 cm above the ground and 10 cm away from walls.

4. ② Leave gaps between cartons for moisture ventilation.

5. ③ Install fans to improve air and moisture circulation.

Cable

Power Cable

Communication Cable

Seal with PE bags, then place in cartons and store indoors.

Inverter

PCS

1. Temperature: Storage temperature shall not be lower than -20℃ or higher than 40℃ for a long time; recommended around 25℃. Provide heating and cooling measures.

2. 2. Humidity: 0–95% RH, non‑condensing, no obvious moisture. For long‑term storage, keep below 85% RH. Use dehumidifiers if needed.

3. 3. Dust prevention: No heavy dust or sand. Seal equipment with stretch film. Take extra protection in dusty areas. Inspect weekly.

4. 4. Fire prevention: Equip with fire extinguishing system or fire extinguishers. No open flames. Apply fireproof clay at the bottom of equipment.

5. 5. Rodent prevention: Check for holes in advance. Install rat baffles. Keep equipment well‑packed and inspected regularly.

6. 6. Coastal area: Strict isolation and protection against salt spray and moisture. Use sealed structure, corrosion‑resistant materials, coatings, surface treatment, corrosion inhibitors. Keep dry; install and maintain unobstructed drainage pipes.

System

System

1. For equipment stored over 6 months: Perform power‑on charge–discharge test every 6 months after checking appearance and internal wiring. Ensure battery SOC is 30%–50% before power‑off.

2. 2. After on‑site installation: Seal the bottom cable entry with fireproof materials.